-
When will the new bridges be completed?
It is anticipated that
all travel lanes will be open by September 2011.
There will still
be isolated, “punch list” type items that need
attention following the opening of the travel lanes.
Some of this
work may require periodic lane restrictions, but for
the most part, the bridge will be fully operational
by September 2011.
-
How long, high and wide
is the new bridge?
The new bridge consists
of two parallel structures, each 5.5 miles long.
Both structures are sixty feet wide and accommodate
three 12-foot travel lanes and 12-foot shoulders on
either side of the travel lanes.
The new bridge
is 21 feet higher than the old Twin Span Bridge, and
approximately 30 feet above the water level. The
bridge features an 80 foot high-rise section to
provide vertical clearance for marine traffic on
Lake Pontchartrain.
-
What happened to the
old bridge?
Workers are taking
pieces of concrete, which once made up the
old bridges, and placing them into Lake
Pontchartrain to create an artificial reef, between
the U.S. 11 bridge and the new Twin Span. There are
plans to build a second artificial reef closer to
the north shore, once crews finish demolishing other
portions of the old Twin Span Bridge.
-
What is the total
project cost, and who is funding it?
The total cost for the
new Twin Span Bridge is approximately $800 million.
The project is being funded by federal tax dollars
from the Federal Highway Administration.
-
Who will be performing
the work?
The Louisiana
Department of Transportation and Development is
administering the project. Project activities are
being coordinated with the Federal Highway
Administration. Boh Bros. Construction Co. of New
Orleans is building the level portion and the
approaches for the new bridge. The 80 foot
high-rise section was constructed by
Traylor/Kiewit/Massman Joint Venture. Volkert
Construction Services is providing construction
engineering and inspection services in support of
the DOTD.
-
How will traffic be
impacted by the construction work for the remainder
of the project? Construction crews are
making preparations to open the eastbound approach
on the northshore of Lake Pontchartrain in September
2011.
The work will
require some temporary daytime lane closures on I-10
which may increase traffic congestion.
Once the eastbound
approach on the northshore is opened, traffic will
be placed in its final configuration and traffic
flow will be restored.
The remainder of
the work will take place off the roadway (Interstate
10) so traffic impacts should be minimal until the
completion of the project.
-
How can I stay current
on information about construction activities?
You can e-mail
questions and comments directly to the construction
team at
twinspanbridge@volkert.com.
You may also contact the DOTD customer service line
at 1-877-4LA-DOTD.